From first email to dismantling

The full sequence, with the working days each stage takes — and the three dates that decide whether a show goes smoothly.

  1. BriefSend the show name, booth number, floor area, budget and any brand guidelines. A floor plan helps but is not required.Day 0
  2. Concept & quoteFloor plan, 3D renders and an itemised quotation within 3 working days. Every material and process is listed separately.3 working days
  3. Sign-offWe revise until you approve. Then we issue construction drawings, material list and power point layout for venue submission.1–2 days
  4. Venue approvalDrawing submission, fire safety, power application, contractor badges — handled by us, progress reported to you.3–7 days
  5. Workshop prefabricationBuilt and pre-assembled in Dongyang. You receive photos of the trial assembly before it ships.5–7 days
  6. On-site buildOur crew installs to the venue's schedule. 2–3 days typical, 3–5 for large stands. Cleaned and handed over complete.2–5 days
  7. Show supportOne-hour on-site response throughout the show for lighting, graphics and structural issues.Show duration
  8. DismantlingRemoval, waste clearance, deposit recovery and site reinstatement to the venue's standard.1 day

Working backwards from opening day

Venues publish their build schedule weeks in advance, and every deadline upstream of it is fixed. This is the countdown we work to for a typical 36 m² timber stand.

Days before openingWhat must be finishedConsequence if late
D-20Brief confirmed, budget agreedA rush design costs more and is worse
D-15Design frozen, drawings submitted to venueDrawings may not clear review in time
D-12Approval returned, fabrication scheduledWorkshop slots are taken by other clients
D-5Stand trial-assembled, photos signed offFaults are discovered on site instead
D-2Materials delivered to venueDelivery permits expire, access is refused
D-1Build complete, cleaned, handed overOvernight work at overtime rates
Red flags

Three dates that decide everything

Design freeze

Drawings must reach the venue 10–15 days before build. After that, every change is a re-submission, and re-submissions do not always clear before the build starts.

Power application

Filed with the drawings. Late applications get leftover capacity — which is often not enough for a coffee machine, let alone a screen wall.

Build slot

Assigned by the venue, not negotiated. Miss it and you build overnight at overtime rates, with the venue's supervisor watching.