From first email to dismantling
The full sequence, with the working days each stage takes — and the three dates that decide whether a show goes smoothly.
- BriefSend the show name, booth number, floor area, budget and any brand guidelines. A floor plan helps but is not required.Day 0
- Concept & quoteFloor plan, 3D renders and an itemised quotation within 3 working days. Every material and process is listed separately.3 working days
- Sign-offWe revise until you approve. Then we issue construction drawings, material list and power point layout for venue submission.1–2 days
- Venue approvalDrawing submission, fire safety, power application, contractor badges — handled by us, progress reported to you.3–7 days
- Workshop prefabricationBuilt and pre-assembled in Dongyang. You receive photos of the trial assembly before it ships.5–7 days
- On-site buildOur crew installs to the venue's schedule. 2–3 days typical, 3–5 for large stands. Cleaned and handed over complete.2–5 days
- Show supportOne-hour on-site response throughout the show for lighting, graphics and structural issues.Show duration
- DismantlingRemoval, waste clearance, deposit recovery and site reinstatement to the venue's standard.1 day
Working backwards from opening day
Venues publish their build schedule weeks in advance, and every deadline upstream of it is fixed. This is the countdown we work to for a typical 36 m² timber stand.
| Days before opening | What must be finished | Consequence if late |
|---|---|---|
| D-20 | Brief confirmed, budget agreed | A rush design costs more and is worse |
| D-15 | Design frozen, drawings submitted to venue | Drawings may not clear review in time |
| D-12 | Approval returned, fabrication scheduled | Workshop slots are taken by other clients |
| D-5 | Stand trial-assembled, photos signed off | Faults are discovered on site instead |
| D-2 | Materials delivered to venue | Delivery permits expire, access is refused |
| D-1 | Build complete, cleaned, handed over | Overnight work at overtime rates |
Three dates that decide everything
Design freeze
Drawings must reach the venue 10–15 days before build. After that, every change is a re-submission, and re-submissions do not always clear before the build starts.
Power application
Filed with the drawings. Late applications get leftover capacity — which is often not enough for a coffee machine, let alone a screen wall.
Build slot
Assigned by the venue, not negotiated. Miss it and you build overnight at overtime rates, with the venue's supervisor watching.
Send us your booth number. Get a 3D concept and an itemised quote.
Tell us the show, the booth number and the floor area. Within 3 working days you get a floor plan, 3D renders and a line-by-line quotation. If the concept misses, you owe us nothing for the design.